Varina Enon Bridge

Location
Location
Richmond, Virginia, United States
Structure
Structure
Bridge
Date completed
Date completed
2021
Owner
Owner
Virginia Department of Transportation
Varina Enon Bridge
In partnership with:
Varina Enon Bridge

Services Applied by VCS Engineering

Ground Penetrating Radar, Impact Echo and Pulse Echo Velocity, Borescope Inspection, Corrosion Evaluation of Post-Tensioning

Project Description

The Varina Enon Bridge carries I-295 over the James River just outside of Richmond, Virginia.  Opened to traffic in 1990 the bridge has been suffering from severe corrosion deterioration due to importer grouting of the external and internal PT tendons.  The problem was first identified when an internal longitudinal tendon failed and during a routine inspection was observed laying on the floor of the girder.  As a result of this tendon failure, the Virginia Department of Transportation (VDOT) requested that an in-depth inspection of all the different structure’s PT tendons to be conducted by NDT Corp.   

Scope

The testing program implemented on the Varina Enon utilized a combination of various nondestructive and inspection methods to effectively assess the potential risk for corrosion deterioration of the tendons.  The testing first started with GPR locating of the internal ducts, then IE testing was conducted over the tendons to locate areas where voiding or defective grout existed.  Once defective grout or voids were identified a small drill hole was made to the duct and a borescope was used to inspect the condition of the defect.  Testing was ultimately conducted of 1,056 tendon ducts in the main cable stay spans and 72 vertical pier tendon ducts.  The testing of the 1,056 superstructure tendons identified 445 ducts with grout voids that ranged from 1-ft to 82-ft in length.   Inspection of the 72 vertical pier tendon ducts found 43 to have voids which ranged from 5 to 30 feet in length.   

Non-Destructive Testing on Varina Enon Bridge

Project Solution 

This testing program located areas where tendon corrosion was occurring due to improper grouting which provided the owner and structural engineer a risk assessment for this structure.  Identifying these grout defects and subsequent corrosion was critical in determining what level of repairs were needed to extend the service life of the bridge.    